How long should the project take?
Context:
The product is under way and progress must be tracked.
Forces:
Too long, and developers become complacent, and you miss market windows.
Too short, and developers become burned out, and you miss market windows.
Projects without schedule motivation tend to go on forever, or spend too much time polishing details that are either irrelevant or don't serve customer needs.
Solution:
Resulting Context:
A project with a flexible target date. Dates are always difficult to estimate; DeMarco notes that one of the most serious signs of a problem in trouble is a schedule worked backward from an end date [DeMarco].
Design Rationale:
MIT project management simulation; QPW; [Brooks]. Most sane projects manage this way.
Next: Developing in Pairs