Ice Palace? Eternal, grieving necropolis? Six towers surrounding death pits -with names of the dead inscribed on the surrounding parapet walls.
"It will be a cemetery, a tourist attraction and a hodgepodge of second-rate "cultural facilities", but it will never again epitomize the commercial dynamism that built New York." R. Jaffe, NY, letter to the NYTimes Mon 9-22-03. BUT, as I just read in a letter to the editor [DailyNews 23-1-06] There is no reason to treat a mass-murder site like a cemetery! DO NOT build a memorial showcasing the killers' success! | |||||
|
The redesigned tower is now "architecture", but the *Governor's* dictates were the major force of the obscene master plan.
"The Twin Towers should be rebuilt as they were...we will not be cowed by terrorists. - As an insurance policy..consulates and offices for Muslim nations [should be made] to occupy space above the 50th floor."
-P. Malinchoc, letter to Editor NY Post 12-22-02. Or MAKE the FBI or CIA take offices at the top of Freedom Tower. See Michael Daly, NY Daily News 9-18-2006.
"Without meaning to, I'm sure, Childs has based his design for Freedom Tower on a symbol of conquest over the Arab world. It gets worse. In modern Europe and the United States the Obelisk is often something else; a funerary monument. The World Trade Center will already be getting a below-ground memorial. The last thing it needs is a quarter mile high tombstone."[-Justing Davidson NYPost 6-30-05 "A high-profile compromise"] - - "The new obelisk-shaped tower..evokes a gigantic glass paperweight with a toothpick stuck on top."[-Nicholai Ourousseff, "A Tower of Impregnability, the Sort Politicians Love" NYTimes 6-30-05] Also see Ourousseff "A Tower That Sends a Message of Anxiety, not Ambition" NYTimes 2-19-2007.] Massive urban destruction, masses of citizens deliberately killed. True horror. Rebuild there? Oh NO. Oh YES. Read my lips -Hiroshima, Nagasaki, Dresden-Coventry-Berlin-London-Tokyo. Not to mention- 19th cent US- Yeah ATLANTA and other burned southern cities, even RENO-CLINTON's WACO [where is the memorial?] and COLUMBINE [so should they close it?] H.S. in your face!...to those WTC families who have been so infected with political correctness over "sacred footprints". | |||||||
|
The Complex Formerly and AGAIN Known at The World Trade Center:
Will cost and finish date ever stop rising? mid to late 2009->Even though WTC 1, the PATH station and memorial are underway, Silverstein is no-go, not having enough $$ to build more than 1 of his towers and is deadlock/no deal with Port Authority for the others. It is such a huge problem that SPR2009 there is preliminary redesign started of nearly WHOLE below-ground infrastructure tied into the Silverstein Towers, from truck dock/security, power supply, PATH vents, etc. that are in jeopardy if Silverstein does not build [NY Daily News 11-8-2009] - Port Authority failed to finalise plans [including siting] and budget for the Central Command 'bunker' for site security and systems are in fiux. NOTHING can open on site if this is not built.
Overly ambitious completion dates, just plain wrong from the start, [Bagli, NYTimes 7-1-2008->] "..set at a time when former Gov. George E. Patraki, Mayor Michael R. Bloomberg and the Port Authority wanted to convey the sense that this most politically, economically and emotionally significant of project would be completed quickly." Why? It's two dozen projects, "[n]ineteen public agencies, two private developers and 101 construction contractors and subcontractors are involved." Besides pressures of dozens of family groups, the community groups, the..."stakeholders" who will be "heard" in the "inclusive" process.
[Fred Siegel, "Stalled at Ground Zero" Wall St. Journal 9-7-2007->] "Despite lofty rhetoric about confounding the terrorists by rebuilding quickly, what followed under the aegis of Gov. George Pataki and Mayor Bloomberg was a quick return to business as usual. In the absence of strong leadership, New York's political culture of ferrociuously clashing interest groups and waltzing elephantine bureaucracies produced, subway repairs aside, almost nothing for five years. PORT AUTHORITY fouled up so badly it said they need into fall 2008 just to redo a budget and timetable which reflects reality for the WTC project for *first* time.
The Towers: It's back WTC 1 [AKA 'Freedom Tower'] rising, cost gone up from $2bil to $3.1bil 2013 completion? : APR 2009 Doubt about need and financing of all the towers, "Renegotiations that could put off the final trade center tower until 2030-NYTimes 4-15-2009.
DBank demolition: JPMorgChase, Merrill etc. Tower 5 plans for that site are abandoned. Dismantling of DBank to be finished not earlier than Larry Silverstein Tower 2, 3 and 4 sites: MAY 2009-in funding trouble. POLs and Port Auth met to re plan retail 'podiums' for these sites. Tower 4 can be compeleted first SIlverstyien says he will have to halt const soon [fall2009] because he has to wait for Port Auth infrastructure to advance. delayed into 2012-13 at least [one delay for example was a 40ft wood/steel retaining wall thru it which he needed PortAuth to remove and they NO because it is just a few FEET outside of tower footprint and so they should not even pay Silverstein a penalty for that. [-see Feiden, DailyNews 10-9-2008] For a bail out Silverstein who is about to run our of insurance money, PORT AUTH is demanding the tribute of giving back rights to one of Tower 2 or 3. Port Auth had owed fines to Silverstein since it missed JUNE 30 2008 deadline for 'delivering' Tower 2 site which was still being excavated [OCT 2008]. -Penalties paid to him OCT 2008 total was $43.8mil [ulimimately from our $$] . Construction of south "bathtub" for truck security entrance and screening was also delayed. Towers 2 and 3 may be delayed to as late as 2030.
Transit Facilities: PATH and NY MTA-Subway: Umm, pardon the expression, are going down the tubes.
After a couple of years of PORT AUTH announcing maintaining major form of the Calatrava plan [cut in scope and quality, increase in security, cut moving part of roof], end of JUN 2008 they may be throwing in the towel as coming in new report [OCT 2 2009] asked for by Gov. Patterson. Cost overruns of original passed 50%. PA only funded $300mil of it.. and the rest is from the FEDs and probably riders and drivers in higher fares and tolls. Announced in MAY 2009 new completion date is Oct 2014, FED "FTA" finding is it could will be early 2015! $1.4bil from us thru Feds as "stimulus" money still may may leave it short funded! When 1st announced the new PATH station was to be completed in 2006!
Every few months Port Authority and MTA announce more cost increases and MTA cuts back scope of the Fulton Transit Centre. It seemed to be going out of existence. The Fulton-Broadway bldg was announced "cancelled" in early 2008 in face of rising costs; rumour was the site was to be paved over, or speculate one of the WTC planned cultural components might take it over. It looks like it is back, with cutback of dome/skylight. The Memorial and Museum: Delayed but site work under way. Cost escalated to $1billion+! The WTC Memorial does NOT include the words or info "SEPTEMBER 11 2001" anywhere! It does NOT include the US flag ANYWHERE! Reflecting Absence, indeed! -press hardly reported this and other such details of the santization of the attack! TODAY the existing "9/11 Timeline" posted along the Church St side is politically corrected and neuters the event! It does NOT include words "attack" or "terrorist /hijacker" etc. DEC 2006 the Mayor sticking his 2c [and million$ toward the memorial plus as chairman] said Police and Fire could be listed together by unit [no rank] and civilians the names are to be engraved RANDOMLY around the tower they died in on wall around the edge of the waterfall pits. It STILL is NOT satisfactory to a group of some of the family members and a TV ad and web protest site is set to begin JAN 24 2007.['google' Christy "Do you know who I am!" Ferer to see a 9-11 widow from hell and what trouble some of them cause..] Deconstruction: DBank and Fiterman: FITERMAN Hall decontamination delayed for years started [SEE MORE->] in 2008, stalled then underway towads late 2009 completion. The City Univ was looking for full $325mil [are $71mil+ short] for the new grander replacement [-Cuozzo NYPost 8-18-2008 called it a "shakedown], don;t know what was worked out. DBank is still in midst of a worse morass, costs rising, and delayed beyond what anyone could have predicted. Criminal charges to contactors, City of NY could be result of summer Grand Jury [scroll box below]. Where were the 4 Bovis inspectors at the time of the fire? Why isn't the Commissioners HEAD rolling over ignored "smoking gun" memo , demolition workers smoking there, removal of standpipe [painted wring color!] MAR 22 2005 memo re FIRE FIGHTNG PLANS for the building? "Half a dozen" agencies -"Regulators, led by the federal Environmental Protection Agency, sent back more that 20 pages in early 2005 filled with suggestions for changes to the first [2004 Dbank deconstruction plan] draft. Six months later, after a second draft was drawn up to meet their specifications, they came up with more than 40 pages of comments and suggestions."[-S. Garland. 9-7-2007, "Negotiations Over Tower Demolition May be Tricky, NYSun] 14 floors taken down by AUG 2007 fire, two firemen dead. St. Nicholas Church relocation and rebuilding negociations "ended" early Mar 2009" and evoling July 2008 offer is rejected. That Port Authority "generous offer" for new site $$$ came with too many strings attached including the height "not to exceed that of the memorial" while the Port Auth claimed the Church was being greedy and wanted confidential info on the plans for the garage. The Church's existing site and nearby substitute site offered both are partly or wholely over new vehicle screening ctr. The Church apparently plans to rebuild on its own land and the Port Auth will take underground building rights by eminent domain, compensating them. [-see Bagli, NYTimes 3-19-2009]
A rebuilt but refined, safer and maybe bigger World Trade Center could have been a LIVING MEMORIAL!... This project is not- should not be- a bunch of buildings of whatever size and plan *plus* a memorial...OCT 2006, Mayor Bloomberg quietly donated $10Mil to the Memorial Foundation and was officially nominated to chair it 10-5-2006.
Gov Pataki's Lower Manhattan Dev. Corp. had it's first meeting in late Dec. 200 *before* these 6 schemes were released. PORT AUTH tried to take solo control of the development process with issuing a request for proposal end of APRIL 2002, but no one knows what came of that. But May 22 2002 the Lower Manhattan Development Corporation and the Port Authority selected the firm Beyer Blinder Belle to coordinate the rebuilding six proposed schemes unveiled at the end of June 2002, after a rushed and confused selection process with stiff requirements that guaranteed fat-cat establishment firms could only survive the selection. These are pictures of models of the scheme -directly to the left]. But instead look Liberty Square, a retro alternative in the pre-war NYC tradition, down below to the right. Beyer is NOT doing the architectural design. Not the designers, Patakis committees orchestrate such a labyrinth of rules, look at we we have gotten so far. The Lower Manhattan Dev. Corp. is composed of members mostly appointed by the Gov. of New York, with some by the Mayor. The Port Authority is a bi-state entity with a board appointed by the Governors of NY and New Jersey. It owns the site, with the bldgs. on long-term lease to L. Silverstein. Muschamp, Times arch. critic says, and I couldn't have said it better about the firm and the process. Ah, FREEDOM TOWER, the big Phase 1 building one had an original completion date in 2008! The GOV was a wise-ass to it call it Freedom Tower..now that is UNdone, which is worse, being P-C and not having the balls to calll it WTC or in this new Obamanation, to retreat from the name of Freedom Tower? -[-The height and name and filling it with government agencies at the start make for a good target, as so many whiners claim any tall tower there would be.] Pataki conferred a meaningless 1776 ft ht on the spire [NO I am NOT making fun of "1776" - using the number in this way IS!] Anyway, this new final Tower was unveiled JUNE 29 2005 (reduced down to 1,368 ft tall before any mast). Bloomberg cut out early, NO ONE from the Port Authority was there. It is a "slender glass obelisk rest on a steel skinned cube." [-69 floors, offices start at 20th fl height above the blast-resistant base]." Slimmer and rotated so it could be set back further from the street and is main mass is as tall as the orig WTC is just high-concept David Childs. What does it have to do with THIS place, its burdens and its potential? "...[T]he quality of the master plan has been sacrificed to the governor's insistence on preserving hollow symbolic gestures."[-Ourousseff, NYTimes 6-30-05]. Note Pataki also forced the renaming of Newark to [Newark] Liberty Airport. The Revisionists and P-C Battle to Control ThoughtThe WTC Memorial Foundation was created in DEC 2004. Its board includes David Rockefeller and the Chairman of AMEX] will eventually oversee the new cultural and memorial facilities is fundraising $500+ million for and assume some of the functions of the LMDC. The board met for the first time 1-5-2005 in secret. NOTE there WAS [denied] taping of the meetings for a proposed documentary, but they got NY Supreme Court to make them private [-see NYTimes on the history of the new WTC and Mem progress, 9-11-2006]. It is a private corporation. ON July 11 2005, the SECY of the Foundation Stefan Pryor resigned who was also the President of the LMDC!-the Daily News had just questioned the propriety of that and need to clarify connections between the Foundation and the LMDC. Memorial Foundation was to receive minimum of $300Mil in govt funds. 3rd meeting July 12 2005. The scheme evolved and was changed over time but escalated in estimated cost that is now in LIMBO! It just kept its resemblance to the original scheme above the ground, as the underground facilities grew in complexity and the original designer was removed from participation. A lawsuit by various family MAR 2006 to prevent construction of the memorial centered on concerns over new construction touching the footprints[!] was dismissed MAY 11 [decision was released MAY 16!]. This was a modified version of the third public version 12-16-04. M. Arad's "Reflecting Absence" was the winner announced Jan 6 2004 out of 5,300 entries chosen Jan 5 2004. Its first revision was the one released to public JAN 14 with trees added to the blank plaza and the cultural and museum bldgs put back into the overall scheme. The 13-member jury and landscape architect P. Walker "surrounded Mr. Arad's work with a tropical rain forest." Two of 4 access ramps were eliminated and the underground labyrinth of museum and memorial facilities grew. The original design was said to be "..[p]robably the most dignified and legible of the eight that were made public in November. [W]ithout relying on machinery or texts or special effects...that minimalism has largely been betrayed, in a way that is typical of every step of the rebuilding process" and further "..am I the only observer to have been struck by the similarity between the stone container for unidentified remains at bedrock level and the Kabaa in Mecca? Look at it.."[-James Gardner NY Sun 1-15-04]. New York is OVER in So Many Ways [but so is YOUR Town!]In NYC are one of the greatest concentrations of talent and wealth in the WORLD, yet the new WTC is so-so [and still non-existant]. BUT this private sector can sure git-r-done, elsewhere. Western architects designed facilities that are unprecedented works of engineering and art for the Beijing Olympics. "Developers in [fast growing commercial centres from Moscow to Shanghai] want to build something that really makes an impact, a super-high-rise tower.".."that's why they pick us [over local firms..[president of a Manhattan based engineering company] -Marks, "NY builders cash in big overseas" CRAIN's NY Business DEC 4-10 2006. The US is third in the number of skyscrapers going up, but nowhere near the tallest buildings in the world.. The Bin Laden group is finishing what became tallest building in the WORLD JULY 11 2007 as it reached 1,680 ft./141 fl., but expected to have some spire way over 2,000 st, the Burj DUBAI U.A.E., is due for 2008 completion/ occupancy. It exceeds Petronas Centre that was already bested in Taiwan by Tapei 101 as tallest in the world. Buildings 500 to 1000 ft. "officially" classified as "skyscrapers" and over 1,000 ft are "super-tall." [Summer 2007] 240 Skyscrapers or super-tall bldgs are under construction in Asia and the Persian Gulf, DUBAI in a boom with 62 of these. The First Round Schemes Made 'ol WTC Seem BrilliantThe revised plans feature somewhat more conventional towers and reworked underground concourses. But PATH is disputed- Even if they are temporary, they are a violation of the sanctity of the site," said Anthony Gardner, chairman of the WTC United Family Group which is part of a pressure group called Coalition of 9-11 Families [-NYTimes, Metro 7-9-03, "Relatives Say Plans Infringe On Twin Towers Footprints" originally, facilities almost exactly as these were part under WTC2]. They pressed for legislation to codify their *nothing on footprints down to the bedrock stance* and threatened the Port Authority over PATH emergency exits and equipment even as PATH line to the temp WTC station ran test trains Oct 22 2003 readying for *NOV 2003* opening. The activists are also used R Giuliani among others to campaign for the Fed govt to take over memorial development preservation of all land in WTC "bathtub" from "bedrock to infinity" yeah an underground deathpit as memorial [not in their opinion somehow!] which is more than half of the total site, including land where ALL redevelopment schemes include bldgs and the PATH line and station are being rebuilt NOW.[-NYTimes 7-1-03]. The2005 lawsuit of about now 1,000 families seeking removal of ALL WTC debris from the Fresh Kills landfill for search for remains for "dignified burial" -[oy its ashes mixed with ashes of the bldgs] may be dismissed as NYC wishes MAR 2008, as judge finally said "be satisfied with a memorial there" 'your' constitutional right are not being violated; NYC took care to sift for remains with smallest sieve of 1/4-inch. They families might settle for relocating all the stuff to a part of Fresh Kills that was not used for garbage. Militant "WTC Families for Proper Burial" pressured NYC in court for removal of up to 1/2 millions tons of debris BACK to WTC site, they a bit of it to be brought back..I did hear much more about that. Jerky Jerseyites?They call the site a cemetery but NO ONE is BURIED in or connected to the basement concrete floor of the WTC. After the collapses WE BREATHED DEAD POEPLE!.They were mostly squished, ground up and burned along with asbestos, steel and concrete. We all know even though the media self-censored most of it that people jumped rather than burn at the upper floors of the towers. Body parts were found even found INSIDE many nearby APARTMENTS -[so, tear THEM down![?]. The Memorial "competition" added requirement of a facility to house unidentified remains, [an "ossuary"] which is to be incorporated into the memorial schemes. "the NJ Governor shouted Aug. 28 2002 no plans to be made by LMDC "over my damned body." [Former] Mayor Giuliani said SEP. 1 or 2 2002 that the WHOLE site should be a memorial. By all their logic, we should *NOW* tear down a big chunk of Park Slope near 4thav 3-5 st because that IS sacred ground..the first battle of the Revolution in AUG 1776 "Battle of Long Island" where hundreds of men, many Marylanders died, losing actually but buying time for George Washington and troops to get away to fight another day. There are other battlefields too, even in NYC. *late JUNE 2003 *[More crazy New Jerseyans Some family members of the killed want Families for Proper Burial filed suit against NYC, Port Auth and LMDC 10-14-04 to bring the ashes from the landfill RETURNED to WTC site memorial. They demonstrated there again SEPT 10 2006 to "demand" return of their loved one "bodies" or remains from Fresh Kill to the WTC site, even though only ashes are left and any unidentified fragments are being held in special preservation at a center at Bellevue for the long run until identified by any means possible and other fragements are to be placed at the site. NJ State Assembly members Linda Stender and Neil Cohen introduced a bill to return 9-11 victims' remains which, *there* are really ashes] from Fresh Kills to Ground Zero." [-NY Post 10-20-2002, too. In late DEC 2003 Gov McGreevey of NJ signed very misguided legislation "..that would direct the Port Authority..to collect the trade center ash from Fresh Kills - which the legislation states, "contains remains of the victims of Sept. 11 , 2001" -and transport it in containers to a future memorial at ground zero. Since this would mean not only digging up more than a million tons of hazardous debris buried on a site owned by New York City, but also passing an identical measure in New York and getting the city to accept the debris, statehouse observers say New Jersey would find such legislation difficult to implement."-NYTimes 12-30-03 Would they really want sifted WTC debris they dug up in 2001-2002 put back? 'Marginal Role for Architecture at Ground Zero'-a blunt critique in NY Times Metro 5-23-2002, by Herbert Muschamp David Childs as architect to actualize Libeskind's scheme doesn't change that - his buildings hum, but they don't sing; witness his Worldwide Plaza at 8av50st, 7 Times Square, and new AOL-Time Warner Center.
| |||||||