Week 23 (October 11-15):

***Click on the thumbnails to see a larger view. Use your browser's Back button to return to this page.***

More delivery craziness - the appliances were delivered on Tuesday. The dishwasher and disposal came, but for some reason the microwave/hood-range was not included. It will come next week. On the bright side, the bedroom furniture was redelivered correctly.

The new blinds went in Monday, and the HI-MACS countertops were installed on Thursday (it's a solid surface material).

The plumber was supposed to come on Friday to finish the kitchen and upstairs bathroom but he didn't. He wasn't here Monday either.

At this point, I'm waiting for them to finish a bunch of small things upstairs, mostly touching up nicks and scratches (and of course the bathroom). Once I'm sure no more work will be done upstairs, I can move up there and empty out the two downstairs bedrooms so they can paint and carpet. Then it will be pretty much done!

For the record, I will have moved everything out of my house while still living here. How do you suppose that happened?

 