Welcome to Deb's House Project
Week 1: Digging starts, cement footings are poured. Week 2: Basement walls are poured. Week 3: Backfill and basement floor. Week 4: Framing of the kitchen floor. Week 5: Framing of the first floor (kitchen walls). Week 6: The roof comes off. Week 7: Framing of the second floor. Week 8: Framing continues, including stairs. Week 9: Roofing, framing of 2nd floor interior, start of electrical. Week 10: Electrical work continues, mobile storage unit is delivered. Week 11: Packing, packing and more packing. Week 12: Installation of windows, plumbing. Week 13: Tearing down the walls! Week 14: Siding, electrical. Weeks 15-16: Vacation, insulation, drywall. Week 17: Plastering. Week 18: Trim work - baseboards, doors, built-ins. Week 19: Front step. Week 20: Painting. Week 21: Paint and carpet upstairs, install kitchen cabinets. Week 22: Template counters; install bathroom and kitchen flooring, bathroom tile. Week 23: Fix kitchen flooring; finish upstairs electrical. Week 24: Install blinds; deliver appliances and bedroom furniture; install kitchen counter. Week 25: Finish plumbing in kitchen and bathroom; move upstairs. Week 26: Install master closet,shower door; tear up old carpet. Week 27: Paint and carpet downstairs; drop-ceiling and retile in downstairs bathroom; living room furniture. Week 28: Finish tiling bathroom; dining room furniture; final walk-through, inspections. [Week 29]: Finish the last few punchlist items, start unpacking, decorating. See the end results here. |